(1) Compliance. The grantee of any permit shall comply with all of the requirements within the small wireless permit.

(2) Post-Construction As-Builts. Within 30 days after construction of the small wireless facility, the grantee shall provide the City with as-builts of the small wireless facilities demonstrating compliance with the permit and site photographs.

(3) Permit Time Limit. Construction of the small wireless facility must be completed within six months after the approval date by the City. The grantee may request one extension to be limited to three months, if the applicant cannot construct the small wireless facility within the original six-month period.

(4) Site Safety and Maintenance. The grantee must maintain the small wireless facilities in safe and working condition. The grantee shall be responsible for the removal of any graffiti or other vandalism and shall keep the site neat and orderly, including but not limited to following any maintenance or modifications on the site.

(5) Operational Activity. The grantee shall commence operation of the small wireless facility no later than three months after installation, unless the City and applicant agree to extend this period, or delay is caused by the lack of commercial power, communications facilities or other events outside of the reasonable control of the wireless provider. (Ord. 03-19 § 2 (Exh. A))